Chube Update August 8/19

Plated parts due in by 8/26 (ASAP expedite requested, so it might be sooner, but alas) for Compact.

Shipments begin immediately after. Will be done FIFO, in batches. (assemble dozens, ship dozens, etc) Resellers will be delivered proportionally to assembly pace. 

Price will increase to $170 ($5 increase over previous expected MSRP) as most inputs have significantly increased in price (copper doubled).

Chube Conduction+Air will begin shipping likely the week after Compacts start shipping once they're back from plating as well. Made the remaining parts after compact parts. 

A note, an opportunity, and the promise of a future conversation:

Look - I'm not happy with how any of this has gone either. I've read quite a few opinions of where I've messed up, what I should have known, how I should have done things, etc etc. I've been responding piecemeal/as I see them, but at this point, I'd love to have a huge session where I can answer questions and share some more details into our adventure in the coming months. 

Here's your chance to submit that advice directly, and/or ask questions that you'd like to know. 
I take the audience I have seriously, just as seriously as I took your trust as you placed these orders. I'll answer every question submitted, and reply to every bit of advice.

I'll even put a bounty on it. You submit some advice that I didn't know/consider/see? I'll send you a spool of our filament. Form link below with more info.

Submit your Questions/Advice here

Machining nerds:
I purposely kept this one short. I'll yap later/make a video. so many things!